Client

Confidential

Timeline

Eight (8) working weeks

Sector

Industrial manufacturing

Project

Replacement of Micro-Perforated Fluidisation Panels with SintAbond™ MESH

Product specified

CFL SintAbond™ MESH 316 Stainless Steel

Objective

Improve durability and gas flow efficiency

Result

Increased productivity, reduced consumption of gas with lower operating costs

Background

The client, a pharmaceutical manufacturing company, faced significant challenges with their existing fluid bed dryer performance. The fluidisation panels, crucial for ensuring gas flow distribution and maintaining process efficiency, were underperforming and prone to damage. This inefficiency and vulnerability led to frequent downtime and complex replacement procedures, adversely impacting operational performance and increased maintenance costs.

To address these issues, the client sought a more durable and efficient alternative that could withstand the rigors of their process, whilst providing the necessary porosity and differential pressure, necessary for effective fluidisation.

Objectives

Durability

Replace easily damaged micro-perforated panels with a more robust solution.

Efficiency

Improve porosity and differential pressure, to provide effective air distribution.

Reduced downtime

Minimise downtime associated with panel damage and replacement.

Energy efficiency

Enhance gas distribution, potentialy reducing consumption.

Solution Provided by CFL

CFL specified a material from their series of SintAbond™ MESH, a sintered multi-layered mesh, manufactured in 316SS. This solution offered the following advantages:

Enhanced durability

The sintered mesh construction provided a harder-wearing alternative to the micro-perforated panels, significantly reducing susceptibility to damage.

High porosity

The design ensured the high porosity necessary for effective fluidisation, maintaining process efficiency.

Improved gas flow

The SintAbond™ MESH structure facilitated increased gas flow, enhancing distribution, optimising process effeciency.

Implementation

01

Needs assessment

CFL collaborated with the client to understand their operational challenges and specific requirements for fluidisation. This included analysing the limitations of the existing micro-perforated panels and identifying opportunities for improvement.

02
Product selection

Based on the assessment, CFL specified the optimum SintAbond™ MESH product for the application. The material specified offers excellent mechanical properties, corrosion resistance, and suitability for high-performance applications. The design focused on optimising the mesh structure to balance durability with the required porosity and differential pressure, to provide effective fluidisation.

03
Installation and testing

CFL provided technical support for the installation of the SintAbond™ MESH panels, ensuring a smooth transition from the original micro-perforated panels. Initial testing demonstrated a much improved gas distribution and the potential to reduce gas flow by approximately 10% due to the increased efficiency of the design.

Results

Future Applications

Encouraged by the performance of the CFL SintAbond™ MESH, the client has requested similar replacements for other equipment on site. This further emphasises the success and potential of the CFL solution in enhancing processes efficiencies across various applications.

Conclusion

The implementation of CFL SintAbond™ MESH provided the client with a highly durable and efficient solution. The robust design and improved gas distribution resolved the issues associated with the original micro-perforated panels, significantly reducing operational costs.

By delivering a customised high performance product, CFL demonstrated its capability to innovate and provide effective solutions that address specific industrial challenges.

Key Takeaways

Innovative design

The SintAbond™ MESH panels offer a superior alternative to micro-perforated panels, enhancing both durability and efficiency.

Operational efficiency

Improved gas distribution and reduced downtime contributed to higher productivity and energy savings.

Client expansion

Success with initial implementation has led to further opportunities for CFL to provide solutions for additional equipment within the client’s operations.

Client Feedback

From an operational perspective, the SintAbond™ MESH panels work a dream. Initial tests indicate we can reduce the gas flow by around 10% as distribution is much improved.

Confidential Client

Operations Manager

Other Case Studies

Kew Technology Ltd, a leader in sustainable energy solutions, relies on advanced syngas filtration technology to optimise their energy production processes. Their syngas filter cassette, an integral part of a commercial scale test plant, experienced a failure due to wear and tear of existing components.
The client, a pharmaceutical manufacturing company, faced significant challenges with their existing fluid bed dryer performance.